|
|
 |
Overview of Task Order Procedures
Following are the M/OP and BGH/HN Agreement on TASC2 Task Order Procedures
The CTO, in conjunction with his or her CO, and with the assistance of technical
staff in BGH if desired, prepares a statement of
work, establishes tangible
results and benchmarks, evaluation criteria, and independent government estimate
(budget). The CTO requests his or her CO to negotiate a Task Order under TASC2
through a MAARD or NMS request. While not required, BGH/HN will be happy to
comment on any statement of work, if requested.
The CTO must assure that the Contractor has an understanding of the appropriate
level of effort that is required by the particular statement of work. To achieve
this, the CTO may (a) request the Contractor to submit a proposed staffing
matrix based upon the Task Order statement of work, or (b) provide the
Contractor with a notional staffing matrix.
The Task Order request (MAARD or NMS Request) will be cleared within and funded
by the requesting USAID unit (Bureau or Mission) and submitted to the
Contracting Officer for processing.
Unless an exception applies, the Contracting Officer issues a Task Proposal Request (TPR) to all contacts at all Contractors under TASC2 via E-mail, fax and or regular mail, with an E-mail copy to Elizabeth Fox in BGH/HN. For complex Task Orders, the CTO should extend the response period. Remember that Contractors are not required to respond to a TPR.
TASC2 has been designed to be a quick response technical assistance mechanism,
but missions should allow contractors adequate time for the preparation of
responses to task proposal requests. At a minimum, contractors will be given
five working days to prepare and submit technical proposals, however, for more
complex or multi-year scopes of work at least four to six weeks should be
allowed. Technical Officers should consult with their Contracting Officers for
advice on the period of time that is reasonable. Missions should be aware that
they may receive an unsatisfactory response to requests for proposals if they do
not allow sufficient time. If time is a constraint, Technical Officers may
consider sending to all TASC2 contractors advance notice or a near final draft of
a pending task proposal request. However, you must have the permission of the
responsible Contracting Officer to send such advance notice, and you must send
it to all TASC2 contractors. Technical Officers should recall that they are not
to have discussions with any TASC2 members about a pending competition or award
until after an award is made. Upon receipt of technical proposals, the CTO will
convene a selection committee to determine the Contractor best suited to provide
the requested services. The Selection Committee may hold discussions with the
Contractors regarding the proposed LOE and their technical proposals. If
necessary, the Contractor may be required to confirm understandings reached in
the discussions. The committee makes its recommendation for award to the CO
through a Selection Memorandum.
The CTO will then prepare the Task Order
documentation, including fund
reservation, statement of work, independent cost estimate and selection
memorandum. Fund reservation will be based upon the CTO's independent government
estimate. Authorized Geographical Code will be 000 (unless a waiver is approved
by the requesting unit, or all funding is provided by a source which authorizes
another geographical code, for example, under a SOAG.)
The Contracting Officer will conduct negotiations with the Contractor, normally
with the participation of the CTO. Note that unlike some other IQCs, labor costs
under TASC2 for U.S. Personnel will be negotiated between the Contractor and the
CO. The negotiated rates for individual U.S. expatriates shall be based on
various factors, including the labor category, market value of the position, and
the individual's salary and/or consultant rate history, but can not exceed
salaries at the ES-6 level (currently $455.36 per day) without a waiver.
After all negotiations are concluded, the CO will finalize the Task
Order, prepare
the negotiation memorandum, obtain the CTO's clearance, and complete the
processing of the Task Order. Mission COs can request Task Order numbers from
Sarah Laws, OP/CIMS in Washington and are asked to copy the message to Judy
Britt OP/SPU. Copies of the Task Order will be distributed by the CO, including
a copy to the TASC Contract CTO. The CO should then inform firms whose proposals
were not selected of the award.
The Task Order will be administered by the CTO, CO and FM of the USAID issuing
unit. Copies of modifications and significant correspondence should be forwarded
to the Contract Technical Advisor, Elizabeth Fox, who is available to assist in
any way possible
The CTO and Contracting Officer will complete a Contractor Performance
Evaluation Report (PER) annually and at the completion of each Task Order, using
AID Form 1420-66. Contractors shall have 30 days to comment on or rebut the assessment, or
may simply concur. Copies of the completed PERs will be forwarded to the
Contract CO for distribution.
NMS states that Contracting Officers shall generally complete Task Order
negotiations and award within 64 calendar days of receipt of an acceptable
statement of work (including tangible results and benchmarks), budget estimate
and selection criteria. However, by working closely with COs, TASC task orders
should be completed in less time.
|
|